The short answer
Where possible, snag before you complete. A pre-completion inspection lets you raise issues while the home is empty, and the New Homes Quality Code expects developers to address warranty-standard defects before completion where possible, or within 30 days. Our survey is equally thorough at either stage, so if you have already moved in, it is not too late.
What each option means
Buying a new build follows a set order: you reserve the home, exchange contracts, and later the developer serves a notice to complete, which tells you the date the home will be ready. You then complete the purchase, collect the keys and move in. Snagging can happen either side of completion.
Pre-completion inspection. A surveyor inspects the finished home after the notice to complete has been served, but before you legally complete. The Code usually expects at least 14 calendar days between the notice and completion, which leaves room for this. The home is empty, so every room is easy to access, and any issues can be dealt with before you move in.
Post-completion inspection. A surveyor inspects after you have completed, whether on the day you collect the keys or in the weeks and months that follow. Issues are reported to the developer through its after-sales service, which the Code expects to run for at least two years.
In both cases the job is the same: find what needs putting right, record it clearly, and give you a report you can send to the developer.
What the Code says about each stage
Under the New Homes Quality Code, a developer registered with the New Homes Quality Board must give you the opportunity to inspect your new home before completion, or to appoint a suitably qualified inspector to do it for you. Version 2 of the Code, which applies to homes reserved from 2nd March 2026, also lets you carry out the inspection yourself using the NHQB checklist, although the developer must warn you that the checklist was designed for professionals and you may miss things.
An inspector you appoint should be a member of a recognised professional body such as RICS or RPSA, they must hold professional indemnity insurance, work within their competence, and use the NHQB's standard Pre-Completion Inspection Checklist (but this may be reproduced in an electronic format, such as a PDF report). Ask any surveyor you are considering to confirm these.
If the inspection finds issues that breach warranty technical standards, the developer is responsible for putting them right, ideally before you complete or within 30 days if that is not possible. The inspection is not meant to delay completion.
After completion, the Code still protects you. It runs from the date you reserved until two years after you complete. The developer must provide an after-sales service for at least two years, settle most issues within 30 days unless there is a significant reason for delay, update you at least monthly if there is a delay, and operate a formal complaints process. If that fails, the New Homes Ombudsman Service is available after 56 days.
So both stages are covered where the Code applies, and a pre-completion inspection adds timing: you can ask for issues to be put right before you move in, rather than after.
A caveat. The Code applies only if your developer is registered and activated, and you reserved your home after its activation date. You can check on the NHQB Register of Developers. Shared ownership, affordable homes and homes bought as a rental or investment are not covered. If the Code does not apply, another consumer code and your warranty provider may still protect you, and it is still reasonable to ask the developer for access before completion.
Is a pre-completion survey a restricted survey?
Some people suggest a post-completion inspection is the better option, on the idea that a pre-completion inspection is somehow limited. We see it differently. Our Accredited Snagging Survey is carried out by the same surveyors, to the same standard and with the same scope, whichever stage you choose.
What differs is the practical position. Before completion the home is empty, you can ask for issues to be dealt with before you move in, and the Code gives you a clear route to do that. For that reason we support the Code and its pre-completion inspection, and we recommend surveying before completion wherever possible.
Booking early helps. We are often fully booked for the next week or two, so please get in touch as soon as you can. We are happy to contact your builder on your behalf to discuss and arrange an appropriate survey date. If we reserve a date for you early, we can adjust it as completion approaches.
Already moved in? It is not too late. A post-completion survey is carried out to the same standard, and the report goes to your developer through its after-sales service. Report early, because some issues, such as damage to surfaces, become harder to pin down the longer you wait.